14 de abril de 2025, 8:29:19 a.m.

Contractors will continue clearing and grubbing activities at the Joe Peed Pump Station site. At the East Middleton Pump Station, plans are underway to complete the installation of erosion control measures, including a temporary skimmer basin.

Subcontractors will also proceed with clearing operations along the pipeline corridors.

8 de abril de 2025, 3:19:36 p.m.

The rain event on April 7, 2025, temporarily halted clearing work by HAREN and KBS. As a result, crews will not be onsite today, April 8, 2025.

KBS, the clearing contractor, plans to work from 7:30 AM to 5:00 PM from Thursday, April 10th to Saturday, April 12th. There will be no work at the E. Middleton site during this period.

HAREN staff will conduct a site visit on Saturday to assess the status of the dewatering pumps.

24 de marzo de 2025, 2:31:02 a.m.

General Contractor, Haren Construction, will begin work to clear both E. Middleton and Joe Peed Lift Station Sites.

Subcontractors from JF Wilkerson will be onsite to manage pipeline clearing.

This process (pipeline clearing) will span a longer distance within the shoulder of the road.

View Project Page
logotipo de sgwasa

Autoridad de agua y alcantarillado del sur de Granville

415 Avenida Central, Suite B

Butner, Carolina del Norte 27509

​

​

TELÉFONO

(919) 575-3367

​

​

FAX

​

​

(919) 575-4547

Archivo

Financiero

Contacto del personal

nuevos clientes

Clientes existentes

© Derechos de autor
bottom of page