top of page

News


I-85 SSI Railroad Tunneling Moves to 24-Hour Operations
Construction on the I-85 Sanitary Sewer Improvement Project (I-85 SSI) is advancing as crews begin 24-hour tunneling operations associated with the railroad bore, beginning September 14, 2026.
2 days ago


Planned Repair - 12th Street in Butner, NC
Crews anticipate completing the repair without interrupting water service. However, a temporary service interruption may be necessary for customers in the immediate area identified on the accompanying map. Customers should prepare for this possibility while work is underway.
2 days ago


Water Main Break - East C Street
Repairs to the water main near East C Street and 20th Street have been completed using a 12-inch wraparound repair clamp. Water service remained available throughout the repair, and customers did not experience an interruption.
6 days ago


Two Week Look Ahead: Closures and Pavement Work
The I-85 SSI Project is moving into the next sequence of field activity as crews transition from Railroad Avenue toward A Street and prepare for upcoming work near 8th and C streets.
6 days ago


8th Street Service Interruption
Butner, NC - Water service is temporarily interrupted along the 300 block of 8th Street while crews repair a corporation stop that was snagged during construction activity.
Crews are working to complete the repair and restore service as quickly as possible. An update will be provided once water service has been restored.
Sep 4


Notice: Cancellation of Regular Board Meeting
Notice is hereby given that the regularly scheduled meeting of the Board of Directors of the South Granville Water and Sewer Authority (“SGWASA”), scheduled for Tuesday, September 8, 2026, at 6:00 pm is hereby CANCELLED.
Sep 3


Golden Pond Unidirectional Flushing Scheduled for September 22nd – 23rd
Butner, NC - SGWASA will resume the Unidirectional Flushing Program plans within Creedmoor's Golden Pond community on Tuesday, September 22, and Wednesday, September 23, 2026.
Sep 2


I-85 SSI Traffic Alert: Multiple Road Closures and Lane Restrictions
Construction is advancing successfully across the I-85 Sanitary Sewer Improvement Project. The following Two Week Look Ahead covers Construction Packages 1 and 2 from August 31st through September 11th, 2026. Under Construction Package 1, JF Wilkerson crews plan to dechlorinate the new 8-inch waterline and collect a bacteriological sample before proceeding with restoration work. Crews will also advance the 20-inch force main leaving Joe Peed. Upcoming work is expected to incl
Sep 2


11th Street Closure Begins August 31st
Pipeline construction associated with the I-85 Sanitary Sewer Improvement Project will begin at 8:00 a.m. on Monday, August 31, 2026, along 11th Street between West B Street and West C Street. Work is expected to continue for approximately four to six weeks, with access limited to local traffic during active construction.
Aug 28


I-85 SSI Project Two Week Look Ahead
The I-85 Sanitary Sewer Improvement Project continues to advance across several active work areas as crews move forward with pipeline installation, sewer testing and restoration, and microtunneling operations.
Aug 21


Temporary Phone Service Advisory
Butner, NC - SGWASA’s telecommunications service provider is conducting emergency system maintenance that may temporarily affect automated call routing. During this work, some callers may experience incorrect routing or find that certain menu selections are unavailable. SGWASA recognizes the importance of reliable and timely access to Customer Service. While the provider works to restore normal operations, customers requiring assistance are asked to email customerservice@sgwa
Aug 20


August Virtual Town Hall Brings Community Questions Into Focus
The session also addressed personal water filters—a topic that prompted public comment and Board discussion. As design advances for an advanced water treatment facility intended to reduce PFAS levels and support EPA compliance by 2029, the program explained how in-home filters compare with a long-term, systemwide treatment solution.
Aug 20


August Board Meeting Advances Financial, Infrastructure and Customer Priorities
August Board Meeting Advances Financial, Infrastructure and Customer Priorities
Aug 18


Lake Holt Levels Improve - No Ongoing Restrictions
SGWASA’s Stage 1 voluntary water conservation measures are no longer in effect.
Aug 14


SGWASA Advances PFAS Treatment Project and Receives AFFF Settlement Funding
South Granville Water and Sewer Authority continues to advance its long-term response to per- and polyfluoroalkyl substances, commonly known as PFAS, through treatment design, pilot testing, permitting coordination, and strategic funding efforts.
Aug 10


Lake Holt Levels Continue to Improve as Voluntary Conservation Remains in Place
Recent rainfall and evolving weather conditions have supported Lake Holt levels rising approximately two feet, which serves as an encouraging improvement for the Granville County community’s water supply.
Aug 4


Rescind Notice
Due to emergency water main repair work performed by SGWASA utility crews on July 31, 2026, on North Main Street in Creedmoor, NC, affected water customers experienced a temporary loss of pressure within the water distribution system.
Based on the laboratory analysis of the water samples collected by SGWASA following the water main break repairs, customers are hereby notified that the System Pressure Advisory is no longer in effect.
Aug 1


System Pressure Advisory
Utility crews conducted an emergency water main repair reported near for an 8" water main break on West E Street. SGWASA water customers experienced a period of no pressure in the water distribution system. Due to this event, a water system pressure advisory is in effect until further notice.
Jul 31


North Main Street Water Main Break
SGWASA received a report of a significant water main break in the 400 block of North Main Street in Creedmoor, NC.
Jul 31


I-85 SSI Project - Central Avenue Re-opens
The Central Avenue road closure is scheduled to end by close of business today, ahead of the original estimated completion date of August 10th, 2026.
Jul 30
bottom of page
