top of page
Construction Workers Measuring

I-85 SSI Project

The South Granville Water & Sewer Authority partnered with engineering experts CDM Smith to conduct the I-85 Sanitary Sewer Improvement Project.

 

This project will replace aging materials to maintain an infrastructure that meets Granville County’s present and forthcoming capacity demands.

Construction Tape.png

DAILY PROJECT UPDATE

View daily field plan information for SGWASA’s I-85 Sanitary Sewer Improvement Project, received from Resident Project Representatives.

Next Update:

May 23, 2026

May 21, 2026

Joe Peed Road Sewer Installation and CP-2 Blasting Activity

CP-1 Updates
Haren crews are continuing pipe installation at the Joe Peed site. JFW crews continue laying gravity sewer main along Joe Peed Road as part of ongoing sewer infrastructure improvement. Autry crews are continuing force main work along West Middleton Drive.

CP-2 Updates
Park Construction crews will continue installing the 36-inch fiberglass reinforced pipe at the launch pit.

Carolina Drilling is scheduled to conduct two controlled blasting activities today at approximately 10:00 AM and 2:00 PM.

Nearby residents, motorists, and property owners may notice temporary noise or vibration associated with this planned construction activity.

Crews continue pipe installation, force main work, and gravity sewer installation.

Work remains active near the Joe Peed site, Joe Peed Road, West Middleton Drive, and the CP-2 launch pit area.

TWLA Updates:

5/21/26, 3:00 PM

Over the next two weeks, I-85 SSI Project crews will continue active sewer infrastructure work across Joe Peed Road, West Middleton Drive, East Lyon Station Road, A Street, and 8th Street. Construction Package 1 crews will continue 24-inch gravity sewer work near Joe Peed Road and 24-inch combined force main installation along West Middleton Drive toward East Lyon Station Road.

Construction Package 2 crews will continue installation from the microtunnel launching pit toward the railroad, and Carolina Drilling will continue blasting activities on A Street. Traffic impacts are anticipated, including a partial closure on 8th Street and a full closure on A Street, with Park coordinating with Hanes Geo.

No planned service impacts are anticipated at this time.

News Updates

bottom of page