TWLA List

April 14, 2025 at 8:29:19 AM
Contractors will continue clearing and grubbing activities at the Joe Peed Pump Station site. At the East Middleton Pump Station, plans are underway to complete the installation of erosion control measures, including a temporary skimmer basin.
Subcontractors will also proceed with clearing operations along the pipeline corridors.

April 8, 2025 at 3:19:36 PM
The rain event on April 7, 2025, temporarily halted clearing work by HAREN and KBS. As a result, crews will not be onsite today, April 8, 2025.
KBS, the clearing contractor, plans to work from 7:30 AM to 5:00 PM from Thursday, April 10th to Saturday, April 12th. There will be no work at the E. Middleton site during this period.
HAREN staff will conduct a site visit on Saturday to assess the status of the dewatering pumps.

March 24, 2025 at 2:31:02 AM
General Contractor, Haren Construction, will begin work to clear both E. Middleton and Joe Peed Lift Station Sites.
Subcontractors from JF Wilkerson will be onsite to manage pipeline clearing.
This process (pipeline clearing) will span a longer distance within the shoulder of the road.